PROJECT PROGRESS
THE STATE OF URBAN HABITAT
CONSTRUCTION UPDATE December 2016

Construction update report on Urbitia Thong Lo as of December 29th 2016

EMC Public Company Limited would like to inform about the construction update of the project Urbitia Thong Lo as of December 29th 2016 with the detail as following

Project overview
- Foundation work has now been fully completed (100%)
- The Seismic Test has been completed (20 tons per test)  
- 50% progress on installment of the temporary soil protection system
- The first raker construction process to help prevent landslide is now 25% completed


For more in-depth information about the construction update of Urbitia Thong Lo please contact our customer service team at 662 – 615 -6100 extension 2036 or email at Panpassa@emc.co.th