CONSTRUCTION UPDATE February 2017

Construction update report on Urbitia Thong Lo as of February 2017

EMC Public Company Limited would like to inform about the construction update of the project Urbitia Thong Lo as of February 2017 with the detail as following

Project overview
- Drilling rigs has been completed at 100%
- Sheet Pile work has been completed at 100%
- Excavation work has been completed at 95%
- Foundation work has been completed at 25%
- Septic Tank work has been completed at 25%  