CONSTRUCTION UPDATE June 2017

Construction update report on Urbitia Thong Lo as of June 2017

EMC Public Company Limited would like to inform about the construction update of the project Urbitia Thong Lo as of June 2017 with the detail as following

Project overview
- Drilling rigs has been completed at 100%
- Sheet Pile work has been completed at 100%
- Excavation work has been completed at 100%
- Foundation work has been completed at 99%
- Septic Tank work has been completed at 100%
- B2 Floor work has been completed at 98%
- B1 Floor work has been completed at 10%    
 
For more in-depth information about the construction update of Urbitia Thong Lo please contact our customer service team at 061-419-7732 or email at customer.service@emc.co.th