CONSTRUCTION UPDATE February 2018

Construction update report on Urbitia Thong Lo as of February 2018

EMC Public Company Limited would like to inform about the construction update of the project Urbitia Thong Lo as of February 2018 with the detail as following

Project overview
- 1st-6th Fl. architectural work ,wall been completed at 100%
- 7th Fl. architectural work ,wall has been completed at 50%
- 8th Fl. architectural work ,wall has been completed at 50%
- 1st-6th Fl. Ceiling work has been completed at 100%
- 7th Fl. Ceiling work has been completed at 50%
- 1st - 4th Fl. Tile work has been completed at 100%
- 5th Fl. Tile work has been completed at 20%
- 1st-4th Fl. walk way has been completed at 100%
- 5th Fl. walk way has been completed at 20%
- 6th Fl. walk way has been completed at 20% 
 
For more in-depth information about the construction update of Urbitia Thong Lo please contact our customer service team at 062-605-4995 or email at customer.service@emc.co.th