PROJECT PROGRESS
THE STATE OF URBAN HABITAT
CONSTRUCTION UPDATE March 2018

Construction update report on Urbitia Thong Lo as of March 2018

EMC Public Company Limited would like to inform about the construction update of the project Urbitia Thong Lo as of March 2018 with the detail as following

Project overview
 - The Architectural work ,wall  on 1st - 7th floor has been completed. 
 - The Architectural work ,wall on 8th  floor has been completed at  90%
 - The Ceiling work  on 1st - 7th floor has been  completed.
 - The Ceiling work  on 8th floor has been  completed at  90%
 - The Tile work  on 1st - 4th floor has been completed.
 - The Tile work  on  5th  floor has been completed at 20%
 - The Walk way  on 1st - 7th floor has been completed.
 - The Walk way  on 8th floor  is under construction.
 
For more in-depth information about the construction update of Urbitia Thong Lo please contact our customer service team at 062-605-4995 or email at customer.service@emc.co.th