PROJECT PROGRESS
THE STATE OF URBAN HABITAT
CONSTRUCTION UPDATE May 2018

Construction update report on Urbitia Thong Lo as of May 2018

EMC Public Company Limited would like to provide the construction update  of Urbitia Thong  Lo as of May 2018,  with the details as following.

 - The Architectural work ,wall on 1st - 7th floor has been completed . 
 - The Architectural work ,wall on 8th floor has been completed at 90%
 - The Ceiling work on 1st - 7th floor has been  completed.
 - The Ceiling work on 8th floor has been  completed at 90%
 - The Tile work on 1st - 4th floor has been completed.
 - The Tile work on 5th floor has been completed at 90%
 - The Tile work on 6th floor has been completed at 45%
 - The Tile work on 7th floor has been completed at 25%
 - The Walk way on 1st - 8th floor has been completed.

For more information about the construction update, please contact our customer service team at  062-605-4995 or e-mail at customer.service@emc.co.th