CONSTRUCTION UPDATE June 2018

Construction update report on Urbitia Thong Lo as of June 2018

EMC Public Company Limited would like to provide the construction update  of Urbitia Thong  Lo as of June 2018,  with the details as following.

- The Architectural work, wall on 1st - 7th floor has been completed . 
- The Architectural work, wall on 8th floor has been completed at 95%
- The Ceiling work on 1st - 7th floor has been  completed.
- The Ceiling work on 8th floor has been completed at 95%
- The Tile work on 1st - 4th floor has been completed.
- The Tile work on 5th floor has been completed at 95%
- The Tile work on 6th floor has been completed at 95%
- The Tile work on 7th floor has been completed at 95%
- The Tile work on 8th floor has been completed at 90%
- The Walk way on 1st - 8th floor has been completed.